The influence of time-dependent phenomena in segmental construction of concrete cable-stayed bridges

2011

Construction stages of a cable-stayed bridge are characterized by a sequence in which geometric configuration, restraints and consequently stress and strain patterns vary many times till the final arrangement is achieved. When construction of concrete bridges is made by cantilever method the influence of time-dependent phenomena becomes significant. In this study an evaluation of stay stressing procedures is given by taking into account creep and shrinkage in cantilever construction of concrete cable-stayed bridges. A methodology of stay stressing is proposed with the final target of reaching the desired geometric configuration. Comparison with classical analyses performed by backward metho…

EngineeringCantileverbusiness.industryStress–strain curveBuilding and ConstructionStructural engineeringBridge (nautical)creepDeckCreepCantilever methodsegmental constructionCable stayedbusinessBridgeCable-Stayed Bridge; Creep; Segmental Construction; Prestress Sequence; Cable ForcesShrinkage
researchProduct

A Mixed Approach for Determination of Initial Cable Forces in Cable-Stayed Bridges and the Parameters Variability

2015

The determination of initial cable forces in cable-stayed bridges is an important first step in design and analysis of the structure under external loads. Adjustments of stay forces are often required during construction in order to assure the requested behaviour of the bridge in terms of final geometrical configuration and internal force distribution. An accurate assessment of the stay tensioning system allows designers to obtain a good result at the end of construction, by considering the parameters involved as deterministic quantities, assuring the observance of the execution tolerances during works. Actual loads and their variations need instead a stochastic approach which can give usef…

EngineeringParameter variabilitylcsh:TE1-450Bridge (nautical)DeckBridge Cable-stayed Parameter variability Probability Staged construction Staylcsh:TG1-470symbols.namesakelcsh:Bridge engineeringMixed approachGaussian functionBridgelcsh:Highway engineering. Roads and pavementsComputer memoryCivil and Structural EngineeringProbabilityCable-stayedStaged constructionbusiness.industrycable-stayed; bridge; stay; probability; staged construction; parameter variabilityBuilding and ConstructionStructural engineeringDistribution (mathematics)symbolsCable stayedClosed-form expressionStaybusinessThe Baltic Journal of Road and Bridge Engineering
researchProduct

Stressing sequence of steel cable-stayed bridges built by cantilevering

2015

The construction of cable-stayed bridges by cantilevering implies several changes of geometry, stress and strain patterns during the assemblage of segments. The main target to be satisfied in the construction process is the achievement of the required final geometry and of a convenient state of stress for self-weight and sustained loads. The sequence of stay stressing and the values of prestressing forces at each stage of segment assembling have the main role for reaching the desired result of design, due to the large redundancy of cable-stayed structures.Among the different procedures proposed in the literature for initial cable force determination, the Partial Elastic Scheme (PES) Method …

Finite element methodPrestressingConstruction processStaged constructionFinite element procedurePrestressing forcescable stayed bridgeGeometryCable stayed bridgesNonlinear behavioursSteel cable-stayed bridgesSettore ICAR/09 - Tecnica Delle CostruzioniGeometric non-linearityOffshore pipelinesCable stayed bridges; Finite element method; Geometry; Offshore pipelines; Prestressing; Construction process; Finite element procedure; Geometric non-linearity; Nonlinear behaviours; Prestressing forces; Staged construction; Steel cable-stayed bridges; Stress and strainStress and strain
researchProduct

Construction stages of cable-stayed bridges with composite deck

2012

A cable-stayed bridge is built by following a construction sequence of different subsequent stages that imply changes of the geometric configuration, restraints and consequently stress and strain patterns. A study is presented about stay stressing sequences in cable-stayed bridges with composite deck for the case of construction made by the cantilever method. Initial cable forces are found through partial elastic schemes of construction stages. Different stay stressing procedures are implemented and a comparison between them is proposed in order to evaluate the differences in terms of deformed shape and internal force distribution of the deck and the pylon. Results can be useful to give pra…

constructionEngineeringCable-stayed bridge; composite section; pretension; stays; stressing sequencebusiness.industryGeometric configurationStress–strain curveComposite numberBuilding and ConstructionStructural engineeringBridge (nautical)DeckSettore ICAR/09 - Tecnica Delle CostruzioniCantilever methodPylonsteelCable stayedBridgebusinessBridge Structures